Hey all, I am putting a 151" x 2" x 15" track under my Phazer and after looking at the tunnel construcion, (multiple pieces of tunnel riveted with a single sheet down the center) I am thinking that it would be possible to widen the tunnel...or even replace the tunnel with an M tunnel...
1. take the tunnel off the sled, (pop several rivets and some nuts),
2. pop the rivets to the center piece,
3. replace the two sides of the tunnel back on the bulkhead on the outside of the bulkhead this time. (Stock they are on the inside)
4. Measure and replace the center piece with a wider sheet,
5. Rivet all back in place, shim the suspension with shims equal to the widening and let r rip.
From my initial measurements a 15" would probably squeeze in the bulk head. (maybe a little shaving required!) Seems like the tunnel is the restriction.
Any thoughts? Can you think of something I'm not thinking of that would prevent this from being an easy change?
Thanks for any input. Please keep it positive!
If only real life was as easy as Paint.
Emery
1. take the tunnel off the sled, (pop several rivets and some nuts),
2. pop the rivets to the center piece,
3. replace the two sides of the tunnel back on the bulkhead on the outside of the bulkhead this time. (Stock they are on the inside)
4. Measure and replace the center piece with a wider sheet,
5. Rivet all back in place, shim the suspension with shims equal to the widening and let r rip.

From my initial measurements a 15" would probably squeeze in the bulk head. (maybe a little shaving required!) Seems like the tunnel is the restriction.
Any thoughts? Can you think of something I'm not thinking of that would prevent this from being an easy change?
Thanks for any input. Please keep it positive!
If only real life was as easy as Paint.
Emery